综合超前地质预报技术在巴朗山隧道施工中的应用

Application of Comprehensive Geological Forecast Technology in the Construction of Balangshan Tunnel

  • 摘要: 采用TSP法+地质雷达法+超前钻孔法组合的超前地质预报模式,对巴朗山隧道进口段进行了超前地质预报,并结合地勘资料和开挖揭露情况与预报结果进行对比分析。结果表明:此种综合超前地质预报组合模式取得了良好的效果,确保了隧道施工安全,并且具有较高的实用性和有效性。本文对隧道综合超前地质预报方法的研究具有一定的理论意义和实用价值。

     

    Abstract: The comprehensive geological forecast model combined with TSP, ground penetrating radar and advance borehole method was used to predict the inlet section of Balangshan tunnel, and contrast analysis was conducted for the forecast results, geological data and the exposing situation of excavation. The result showed that the comprehensive geological forecast model had a favorable effect, the safety of tunnel construction was ensured, and this model had higher practicability and effectiveness. This article had theoretical significance and practical value for the research of comprehensive geological forecast in tunnels.

     

/